The Versatile Test Reactor (VTR) was a project by the U.S. Department of Energy to build a fast-neutron test reactor by 2026. Funding for the project was canceled in 2022.
After the Fast Flux Test Facility and the Experimental Breeder Reactor-II (EBR-II) were decommissioned in 1992 and 1994, respectively, the United States was left with no fast-neutron reactor in its fleet. Fast-neutron research was limited to a few restricted reactors located in Russia, including the BOR-60. To address this problem, the Nuclear Energy Innovation Capabilities Act of 2017 included a provision directing the Department of Energy to begin planning for a fast-neutron energy source. Congress included $35 million in 2018 and $65 million in 2019 in the budget in support of this. In February 2019, VTR cleared Critical Decision 0, demonstrating a mission need requiring investment, the first in a series of project approvals. At that time, Secretary of Energy Rick Perry announced the start of the Versatile Test Reactor Project. In November 2019, Battelle Energy Alliance, the organization that manages Idaho National Laboratory, announced an Expression of Interest (EOI) seeking an industry partner to design and construct the VTR. In January 2020, a collaboration between GE Vernova Hitachi Nuclear Energy (GVH) and TerraPower supported by Energy Northwest was announced.
The potential building sites for the VTR were Oak Ridge National Laboratory and Idaho National Laboratory.
Funding for the project was canceled in 2022.
Four national laboratories â Idaho National Laboratory, Argonne National Lab, Los Alamos National Lab, and Oak Ridge National Laboratory â worked with universities and the commercial nuclear industry to come up with conceptual designs, costs and schedule estimates, and support.
The most likely proposed design was a sodium-cooled 300 megawatt reactor based on GVHâÂÂs PRISM reactor. The proposed first fuel would be a uranium-plutonium-zirconium alloy fuel. Such an alloy fuel was tested previously in the EBR-II reactor. Later reactor fuel was proposed to consist of other mixtures and varying enrichments of uranium and plutonium and could have used other alloying metals in place of zirconium. There were no power generating facilities planned for the VTR.
The Department of Energy Office of Nuclear Energy, Nuclear Energy Advisory Committee report "Assessment of Missions and Requirements for a New U.S. Test Reactor" recommended the development of a US domestic fast-neutron test capability. The considerations for such a capability included:
These planned capabilities were roughly similar to the capabilities of the sodium-cooled fast neutron 400MWth test reactor Fast Flux Test Facility, located at the Hanford Site in the state of Washington, which was decommissioned in 1992.
The preliminary requirements that met these considerations included:
Edwin Lyman, senior scientist and acting director of the Nuclear Safety Project at the non-profit Union of Concerned Scientists, questioned the need for a fast-neutron reactor, stating that existing facilities could be utilized to produce fast neutrons. "There is nothing good about these reactors," he said. "I think there is a love of plutonium in the [Energy] Department that is irrational."
The breeder design of the reactor produces more fissile material in the form of plutonium, resulting in proliferation fears.