Uttara North (, romanised: Uttora uttor) is an elevated metro station of the Dhaka Metro Rail's MRT Line 6. This station is located in Uttara, a neighbourhood of Dhaka. It was opened on 29 December 2022.
The Uttara North Metro Station was constructed under "Package CP-03". The notification of application for construction of raised bridges for stations and railways was published on 30 June 2015 and the last date for submission of applications was 9 September 2015. The Italian-Thai Development Public Company Limited received the work contract for "Package CP-03". The agreement was signed in a ceremony on 3 May 2017, and construction work started on 2 August 2017. It was inaugurated on 28 December 2022 and opened for use on the next day.
Bangladesh Road Transport Corporation provides shuttle bus service from the station to House Building.