Naharlagun railway station is a railway station located in Papum Pare district of Arunachal Pradesh. It is about to the state capital Itanagar.
History
Initial survey for the first rail link to Arunachal, HarmutiâÂÂNaharlagun line, was conducted in 1997 and the project was sanctioned in 1996âÂÂ97 Railway Budget as a metre-gauge line. The engine trial run was completed on 15 October 2012, but the railway station and line were operationalised on 7 April 2014. On the same day a NaharlagunâÂÂDekargaon Passenger was inaugurated.
Facilities
The station has three platforms.
Trains
The trains originating/halting at Naharlagun are as follows:
- 15618/ NaharlagunâÂÂShokhüvi Donyi Polo Express
- 22411/ NaharlagunâÂÂAnand Vihar Terminal Arunachal AC SF Express
- 12087/ NaharlagunâÂÂGuwahati Shatabdi Express
- 15908/ NaharlagunâÂÂTinsukia Intercity Express
- Naharlagun â Dekargaon Passenger
Railway in Arunachal
Existing
Existing operational rail lines are.
- HarmutiâÂÂNaharlagun line, 20 km from Harmuti in Assam to Naharlagun near Itanagar in Arunachal, is operational and electrified. Initial survey was conducted in 1997 and the project was sanctioned in 1996âÂÂ97 Railway Budget as a metre-gauge line. The engine trial run was completed on 15 October 2012, but the railway station and line were operationalised on 7 April 2014. On the same day a NaharlagunâÂÂDekargaon Passenger was inaugurated.
- DekargaonâÂÂBhalukpong Line, 63 km operational line continues to provide vital rail access to the western part of Arunachal Pradesh, connecting Bhalukpong on Arunachal-Assam border with the broader Indian railway network.
Under-construction
These lines have been sanctioned, and active physical construction work is ongoing.
- TinsukiaâÂÂDambuk line, ~300 km via Tinsukia (Longpatia)âÂÂPasighat via Kanubari, Deomali, Lekhapani, Jairampur, Kharsang, Miao, Diyun, Tezu, Bhishmaknagar, Roing, and Dambuk, survey under progress as of Feb 2023.
- BhalukpongâÂÂTawang line, INR 70,000 crore ~201.46 km long link declared as the "Strategic Project" involves extensive tunneling for estimated 80% of the route, Detailed Project Report (DPR) completed and submitted to the Ministry of Defence on Feb 2023 but no physical construction has yet commenced as of July 2025.
- NaharkatiaâÂÂDeomali line, â¹1260.13 crore 21.13 km link, survey completed but no progress made due to financial unviability as of July 2025.
See also
References