my-server
← Wiki

High-voltage substations in the United Kingdom

The high-voltage (400kV and 275kV) electricity substations in the United Kingdom are listed in the following tables. The substations provide entry points to, and exit points from, the National Grid (GB) or Northern Ireland Electricity Network. Entry points include power stations, major wind farms and inter-connectors from other countries and regions. Exit points are to lower voltage (275kV, 132kV, 66kV and 33kV) transmission and distribution substations which are also shown in the tables.

History

The first high-voltage substations in Britain were built as part of the National Grid in 1927–1933 by the Central Electricity Board under the provisions of the Electricity (Supply) Act 1926. The substations and the grid operated at 132kV and provided local and regional inter-connections. Higher voltage substations were built as part of the super-grid designed for the bulk transfer of electricity which began to operate from 1953, firstly at 275kV then from 1965 additionally at 400kV. The first 400kV line was the 150 mile section between West Burton power station in Nottinghamshire and Sundon substation in Bedfordshire; the line had a capacity of 1,800 MVA per circuit. The first 400kV substations in Scotland were commissioned in 1972 associated with the line from Hunterston, Ayrshire to Neilston, Renfrewshire.

From 1958 the super-grid and its substations were built by the Transmission Project Group within the Central Electricity Generating Board and included architects and landscape architects. The 400kV super-grid reduced the number of lines and substations and therefore the number of amenity objections. Some substations in urban areas were installed in enclosed structures but the majority were in the open. The appearance of substations, and their visual impact, was improved using earth mounds and trees. Between 1968 and 1973, 725,000 tall trees, 915,400 smaller trees and 17,600 ground cover plants had been used to screen substations. The substation at Sundon, Bedfordshire adjacent to the M1 motorway was screened with a beech hedge, and at Bishop's Wood in Worcestershire the substation was built within an existing wood. In 1972 a Mark II low profile 400kV substation was commissioned, the first was at Wymondley, Hertfordshire. The substation used lighter support structures and the height was reduced from 72 ft to 53 ft (21.9 m to 16.1 m).

The rapid development of the 400kV system is demonstrated in the numbers of new substations that were being built: in 1971 ten 400kV substations were commissioned by the CEGB, these were: Pheasant Farm, Abham, Didcot, Exeter, Hinkley Point, Indian Queens, Landulph, Melksham, Drax and Harker. By 1973 there were sixty-one 400kV substations. In 1979 there were a total of 201 (275kV and 400kV) substations. By the time of privatisation of the British electricity industry in 1990 there were 212 substations operating at 275kV and 400kV, and a total of operating at 275kV, and circuit at 400kV. In 2020 there were 179 400kV substations and 137 275kV substations.

Centralised co-ordination of electricity supplies in Northern Ireland began with the establishment of the Electricity Board for Northern Ireland in 1931. The Northern Ireland Electricity Service was established on 1 April 1973 by the Electricity Supply (Northern Ireland) Order 1972. The integrated electricity network was built in the late 1960s and early 1970s. In 1979, the system comprised of 275kV lines, of 110kV line, and of distribution mains.

Owners and operators

The 275/400kV grid and substations in England and Wales are owned and operated by National Grid Electricity Transmission. It also operates the grid and substations in Scotland although the systems are owned by ScottishPower and Scottish & Southern Energy. In Northern Ireland grid and substations are owned and operated by Northern Ireland Electricity Networks Limited (NIE Networks).

England and Wales

400kV substations

The 400kV substations in England and Wales and their interconnections are given in the following table. The identification codes (e.g. 4YF) for the interconnecting lines and the lower voltage transmission, if any, from the substation are also given.

275kV substations

The 275kV substations in England and Wales and their interconnections are given in the following table. The lower voltage transmission, if any, from the substation is also given.

Scotland

400kV substations

The 400kV substations in Scotland and their interconnections are given in the following table. The identification codes for the interconnecting lines and the lower voltage transmission, if any, from the substation are also given.

There are two interconnections between England and Scotland. On the west coast the 400kV overland line between Harker substation in Cumbria and Gretna substation, Dumfries and Galloway. On the east coast the 400kV line between Stella West substation, Tyne and Wear and Eccles substation, Borders.

In addition the Western HVDC underground and sub-marine link connects Flintshire Bridge Converter station, in Flintshire Wales, to the Western HVDC Converter station near Hunterston.

275kV substations

The 275kV substations in Scotland and their interconnections are given in the following table. The identification codes for the interconnecting lines and the lower voltage transmission, if any, from the substation are also given.

The Moyle Interconnector provides a high-voltage link between the Scotland and Northern Ireland 275kV systems.

Northern Ireland

275kV substations

There are no 400kV systems in Northern Ireland; the highest transmission voltage is 275kV. The substations and their interconnections are given in the table. The lower voltage (generally 110kV) transmission from the substation is also given.

See also

References