Ghatampur Thermal Power Station

NUPPL- GTPP (Neyveli Uttar pradesh Power Limited -Ghatampur Thermal Power Project) is a coal-based thermal power plant located in Ghatampur in Kanpur district, Uttar Pradesh, India. The power plant is owned by the Neyveli Uttar Pradesh Power Limited a joint venture between Neyveli Lignite Corporation (51%) and Uttar Pradesh Rajya Vidyut Utpadan Nigam (49%).

Status update

  • Jan 2015: The land acquisition is completed.
  • May 2015: South Pachwara Coal Block allotted to NLC India ltd for GTPS Project. MDO selection under progress
  • Jun 2015: MoEF issued Environment Clearance on 17-Jun-2015
  • Feb 2016: Centre to consider 1,980 MW Ghatampur project in Kanpur soon.
  • July 2016: Centre approved for installation of Ghatampur Thermal Power Project (GTPC) of 1980 MW (3 X 660 MW) capacity through a joint venture company named "Neyveli Uttar Pradesh Power Limited (NUPPL)" formed jointly by Neyveli Lignite Corporation Limited (NLC) and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL).Untitled Page
  • October 2016: Construction starts
  • June 2021 inspection of railway line to power plant by railway DRM

COMMISSIONING OF UNITS:

Unit-1: 72Hrs continuous full load (660MW) Trial operation of is completed on 03-12-2024. Commercial operation commences on 12-12-2024.

Unit-2: First synchronization with 765kV grid on 21-07-2025. 72Hrs continuous full load (660MW) Trial operation is completed on 23-11-2025. Commercial operation commences on 09-12-2025.

Capacity

The planned capacity of the power plant is 1980 MW. The power plant is secured with coal supply.

The plant has a power purchase agreement (PPA) with Uttar Pradesh Power Corporation (UP Power Corporation) and Assam:

  • Uttar Pradesh Power Corporation: The plant supplies 75.12% of its power to UP Power Corporation.
  • Assam: The plant will supply 24.88% of its power to Assam. As of now, it is shared by Northern states