The Eastern Africa Power Pool (EAPP), is a collaborative effort by eleven countries in Eastern Africa to interconnect their electricity grids and take advantage of excess capacity within the network and facilitate trade of electric power between the members.
The secretariat of the Eastern Africa Power Pool organisation is located at Wereda 02, House 059, Bole Sub City, in Addis Ababa, the capital and largest city of Ethiopia.
In February 2005, seven countries in the Eastern African region came together because they saw mutual benefit in having one power pool. The original countries were, Burundi, Democratic Republic of the Congo, Egypt, Ethiopia, Kenya, Rwanda, and Sudan. Later, Tanzania (2010), Libya (2011), Djibouti and Uganda (2012) joined the pool.
The objectives of the Eastern Africa Power Pool include (a) the reduction of power costs within the region (b) facilitation of power trade between the members (c) increasing energy availability to citizens of member countries (d) increase the grid security of the member countries.
As a prerequisite to the success of these efforts, power grid interconnections between the member countries need to be established. Such interconnections include the interconnection between Ethiopia and Kenya via the SodoâÂÂMoyaleâÂÂSuswa High Voltage Power Line
Other such linkages are the BujagaliâÂÂTororoâÂÂLessos High Voltage Power Line, between Uganda and Kenya, the IsinyaâÂÂSingida High Voltage Power Line, between Kenya and Tanzania, the KawandaâÂÂBirembo High Voltage Power Line, between Uganda and Rwanda, the NkendaâÂÂMpondweâÂÂBeni High Voltage Power Line, between Uganda and the Democratic Republic of the Congo. and the KarumaâÂÂJuba High Voltage Power Line between Uganda and South Sudan. In 2022, construction work began on the KigomaâÂÂButareâÂÂNgoziâÂÂGitega High Voltage Power Line to connect the electricity grid of Rwanda and Burundi.
The table below, outlines the installed capacity, peak demand and the excess capacity or deficit for each of the eleven countries in the Eastern Africa Power Pool, as of June 2019.
The member countries of the Eastern Africa Power Pool and their respective electricity utility companies are listed in the table below.
Some of the transactions among EAPP member states include the following: In July 2022, Kenya signed a 25-year power purchase agreement with Ethiopia, where the latter will sell 200 MW of electric power to the former starting 1 November 2022 for the first three years. Thereafter the amount sold will increase to 400 MW for the remaining 22 year of the contract.
The Independent Regulatory Board (IRB) is an organ of EAPP. The IRB is mandated to establish, monitor and coordinate trade in electricity between the member countries of the EAPP.
Previously hosted at the EAPP in Addis Ababa, Ethiopia, the IRB was given more autonomy in 2012 and was allowed to exercise its independence. In May 2023, the Cabinet of Uganda approved hosting the headquarters of the IRB of the EAPP and granted it diplomatic status. The ERA of Uganda offered premises in Kampala for the IRB to rent.
In December 2023, the African Development Bank approved a loan of US$5.4 million to equip the new headquarters. The World Bank also named the consultant to design the trading platform.