The Amgalan Thermal Power Plant () is a coal-fired power station in Bayanzürkh, Ulaanbaatar, Mongolia.
The power plant was commissioned in November2015. On 4December2015, the opening of the power plant was officiated in a ceremony preceded by Energy Minister Dashzeveg Zorigt and other government officials. In June2022, expansion work of the power plant started to expand its generating capacity.
The power plant has an installed capacity of 348MW. It consists of three steam turbine with each rated at 116MW. The power plant supplies electricity mostly to the eastern part of Ulaanbaatar. It also acts as a district heating for Ulaanbaatar.
The power plant was constructed with a cost of US$75.9 million. It was built with a concession with China Machinery Engineering Corporation.